Running fiber between two buildings isn’t always possible: the excavation permit doesn’t come through, a road crossing is blocked, the land belongs to someone else or there isn’t enough time. In this case, a point-to-point (PtP) wireless bridge is the practical way to connect the buildings to the same enterprise network. Making the bridge run stably isn’t just a matter of pointing the antennas at each other, though; the line of sight, Fresnel zone, link budget and frequency choice must be calculated. Below we give these calculations with example values for links between enterprise buildings, and list installation mistakes you may encounter and an acceptance checklist.
Wireless bridge or fiber?
In capacity, latency stability and independence from weather, fiber is always ahead. Think of a wireless bridge as an interim solution or a backup link. A starting point for the decision:
| Criterion | Fiber | PtP wireless bridge |
|---|---|---|
| Capacity | Scales with the optical module | Limited by channel width and modulation |
| Latency | Low and constant | Low but can vary |
| Installation time | Long due to excavation/permits | Short |
| External factors | Excavation damage | Line-of-sight obstruction, wind, rain (at higher bands), interference |
| Life cycle | Long-lived passive infrastructure | Active device; firmware and hardware refresh |
If a long-term backbone is being planned across the campus, campus backbone fiber design is considered first; the bridge is positioned as a temporary link until the fiber is completed or as a backup to the fiber line. A “temporary” bridge running as the permanent backbone for ten years isn’t a rare sight in the field either; design it accordingly.
Line of sight and the Fresnel zone
It isn’t enough for the two antennas to see each other. A radio wave occupies an ellipsoidal volume around the straight line between the antennas; this is called the first Fresnel zone. A roof edge, tree, crane or building corner entering this volume causes serious signal loss even if the line of sight looks clear. The practical rule: at least about 60% of the first Fresnel zone radius should be unobstructed.
First Fresnel zone radius (m):
r = 17.32 × √( d1 × d2 / (f × D) )
d1, d2 : distance of the point to each end (km)
D : total distance (km), f : frequency (GHz)
Example: D = 2 km, f = 5.5 GHz, midpoint (d1 = d2 = 1 km)
r = 17.32 × √( 1 / 11 ) ≈ 5.2 m → 60% clearance ≈ 3.1 m
Example: D = 0.5 km, f = 60 GHz, midpoint
r = 17.32 × √( 0.0625 / 30 ) ≈ 0.8 m
At low frequencies and long distances, the Fresnel zone is measured in meters; that’s why antenna height is often increased with a mast on the roof. Installations that mount the antenna at parapet level and bury half the signal in the roof edge are among the mistakes you may encounter. On links over a few kilometers, earth curvature also comes into the calculation: assuming a standard atmosphere (k = 4/3), the curvature-induced bulge at the middle of a 10 km link is about 1.5 meters. On a short link between buildings this value can be ignored. During the survey, also note structures to be built in the future, tree growth and temporary obstacles such as cranes that will work along the path. Trees grow every spring.
Link budget: a worked calculation
The link budget is the calculation of the signal level reaching the receiver. Its components: transmit power, antenna gains, cable/connector losses and free-space path loss (FSPL).
FSPL (dB) = 20·log10(d_km) + 20·log10(f_MHz) + 32.44
Received level (dBm) = Ptx + Gtx − Ltx − FSPL + Grx − Lrx
Fade margin (dB) = Received level − Receiver sensitivity
Example: 2 km, 5500 MHz
FSPL = 6.0 + 74.8 + 32.4 ≈ 113.3 dB
Assumption: permitted EIRP upper limit for this band is 30 dBm (example value;
to be verified with the regulator), device with an integrated antenna (cable loss ≈ 0)
Scenario A – 23 dBi antenna:
Ptx = 30 − 23 = 7 dBm
Received = 30 − 113.3 + 23 ≈ −60.3 dBm
Sensitivity for the target modulation (datasheet, example): −65 dBm
Margin ≈ 4.7 dB → insufficient
Scenario B – 29 dBi antenna:
Ptx = 30 − 29 = 1 dBm
Received = 30 − 113.3 + 29 ≈ −54.3 dBm
Margin ≈ 10.7 dB → more stable
The real lesson of the calculation: the EIRP limit restricts the total on the transmitter side; receive antenna gain isn’t included in this limit. That’s why a high-gain antenna increases the received level even if transmit power is lowered. A narrow beam also reduces interference coming from the sides. The cost is more sensitive alignment and susceptibility to wind-induced sway.
The fade margin target is set according to distance, band and how critical the link is. A margin of a few dB means the target modulation drops at the first adverse condition. Polarization mismatch, radome loss and, if there’s an external antenna, cable and connector losses are also added to the calculation. Sensitivity values on datasheets are given separately for each modulation step; the calculation is done for the targeted step, not the value of the best step.
Frequency band selection and regulatory conditions
| Band | Typical use | Strength | Limitation |
|---|---|---|---|
| 5 GHz | Short–medium distance between buildings | Equipment widely available, little affected by rain | Crowded band, interference, DFS |
| 60 GHz (V-band) | Short links of a few hundred meters | Wide channel, high capacity, narrow beam | Oxygen absorption, rain effect, short range |
| 70/80 GHz (E-band) | High-capacity medium distance | Very high capacity | License or registration requirement depending on the country, rain effect, cost |
| Licensed microwave bands | Long distance, critical link | Protection against interference | Licensing process and fee |
In the 60 GHz band, absorption caused by atmospheric oxygen is about 15 dB/km at sea level; this band provides both capacity and natural interference isolation at short range. While the effect of rain is practically negligible at 5 GHz, at 60 GHz and above heavy rain can consume the fade margin. At higher bands, the target isn’t capacity in clear weather but keeping the link up on a rainy day.
Which frequencies can be used unlicensed, EIRP limits, DFS and outdoor conditions vary by country. In Turkey, current conditions should be verified against the regulations of the Information and Communication Technologies Authority (BTK); the harmonized standard in Europe for 5 GHz RLAN equipment is ETSI EN 301 893. Selecting the correct country code in the device software is the first step to preventing unauthorized channel or power use. A bridge running with the default out-of-the-box country code is a situation you may encounter.
Antenna alignment and mounting
- Coarse alignment: The antennas are pointed with a compass and inclinometer according to the azimuth and tilt angle calculated from map coordinates.
- Fine alignment: Using the device’s alignment mode, an audible tone or the RSSI indicator in the interface, first one end and then the other is adjusted in small steps. The target is a received level within a few dB of the value in the link budget. A value noticeably lower than calculated points to side-lobe alignment or a Fresnel obstruction.
- Chain balance: On dual-polarization devices, the received levels of the horizontal and vertical chains should be close to each other. A noticeable difference is a sign of side-lobe alignment, a polarization error or a partial obstruction.
- Mechanical fixing: The mast should be sturdy enough to withstand wind load; after alignment, all bolts are tightened and marked. With a narrow-beam antenna, even a small mast sway affects the link.
- Grounding and lightning protection: The outdoor device, mast and cable entries are grounded; a surge protector is used at the building entrance. Details are in the telecommunications grounding and bonding article.
Throughput, latency and weather conditions
The value on the datasheet is usually the physical layer rate and often the sum of both directions. Usable TCP throughput stays noticeably below this, depending on protocol overhead, the downlink/uplink ratio in TDD (time-division duplex) operation and the modulation step. Many PtP devices use vendor-specific time-division protocols instead of the standard Wi-Fi access method; they give more predictable latency in an environment with interference, but require both ends to run the same vendor and compatible firmware. Updating firmware at only one end can bring the link down.
- Adaptive modulation: When signal quality drops, the device moves to a lower modulation; the link doesn’t drop, but capacity decreases. Users report this as “it got slow.” In the monitoring system, modulation step and received level should be tracked together; for SNMP monitoring, the SNMPv3 configuration article is a guide.
- Capacity plan: The load the bridge will carry (server access, backup, voice, cameras) is added up and compared with the modulation step under the worst weather conditions.
- Redundancy: On a critical link, a backup path can be built with a second bridge (on a different band) or a mobile line. If there are two layer 2 paths, redundancy must be designed correctly with STP or at the routing layer to prevent loops. A single bridge is a single point of failure.
- MTU and VLANs: The bridge must support the VLAN tags to be carried and the required MTU size; otherwise ping passes and large packets are silently lost.
Additional topics for bridges carrying camera traffic, such as bitrate calculation and recording server location, are covered on the camera side in the wireless camera bridge design article.
Installation and acceptance checklist
- Line of sight and Fresnel zone clearance were verified during the survey; possible future obstructions were noted.
- The link budget was calculated; a fade margin for the target modulation was defined.
- Frequency, channel, EIRP and country code comply with regulatory conditions.
- The received level is close to the calculated value; the polarization chains are balanced.
- Throughput tests were done in each direction separately and simultaneously; the results are on record.
- Latency and packet loss were measured with a test lasting several hours.
- Grounding, surge protection and mechanical fixing are complete.
- The management interface is on the management VLAN; default passwords were changed, and firmware is current.
- Received level, modulation and link status were added to the monitoring system; alarm thresholds were defined.
- Installation report: coordinates, azimuth/tilt, channel, photos and test results were delivered.
The survey and installation of a bridge between buildings fall within our wireless network installation service, and the mast, cable route and grounding side within our structured cabling and low-voltage infrastructure service.
Frequently asked questions
Why does the Fresnel zone matter if the line of sight is clear?
A radio wave isn’t a straight line; it occupies an ellipsoidal volume around the antenna axis. A roof edge or tree entering this volume attenuates the signal even if the line of sight is clear. At least about 60 percent of the first Fresnel zone should be unobstructed.
Doesn’t a higher-gain antenna exceed the EIRP limit?
On the transmitter side, as antenna gain increases, transmit power is reduced and the EIRP limit is respected. Antenna gain on the receiver side isn’t included in EIRP; that’s why a high-gain antenna increases the received signal and fade margin while staying within the limit.
Why isn’t the speed on the datasheet achieved in the field?
The value on the datasheet is usually the physical layer rate and is often the sum of both directions. Because of protocol overhead, the TDD direction ratio and modulation drops depending on signal quality, real TCP throughput is noticeably lower.
What distances is a 60 GHz bridge suitable for?
Because of oxygen absorption and the effect of rain, 60 GHz is a short-range band; typical use is links between buildings a few hundred meters apart. The exact range should be calculated with the device’s link planning tool and local rainfall conditions.